Gantt Chart
This report shows issues as a linked series of dependent tasks. Tasks are represented on the Gantt chart by a bar. The length of the bar represents the duration of the task. The duration is either the estimated time required to complete the task or the actual amount of time spent — whichever is greater. Each issue is assigned a start date based on the report start date and the duration that is assigned to predecessor tasks.
The Gantt chart uses the standard finish-to-start dependency relationship. This means that predecessor tasks and subtasks must be finished before work can begin on tasks with dependency links. Subtasks show a start-to-start dependency relationship with other subtasks that do not have dependency links.
The report supports capacity limitations. This option lets you measure how much time is required to finish all of the estimated tasks with a set number of resources. You can use this setting to judge whether you can finish your tasks on time with your current resources and measure how much faster you can complete these tasks when you add resources to the team.
When the report is calculated, the start date, end date, and total number of working days are displayed at the top of the page. For charts with unlimited capacity, you can toggle the presentation to show the actual or estimated duration for each task on the chart. On charts with limited capacity, you can display the estimated view when you remove the spent time field from the report settings.
- The Estimated view shows how much time was estimated for each task. Tasks with dependency links are set to start when the predecessor task is estimated to finish.
- The Actual view includes the amount of time that was spent on each task. Tasks with dependency links are set to start when the predecessor task is actually done. When a predecessor task is completed before the estimated finish date, dependent tasks are scheduled to start earlier. If a predecessor task takes longer than estimated, the dependent tasks are delayed.
The following options are available in both views:
- Move the pointer over a bar to display detailed information for the corresponding task. For a detailed description of these values, see Calculations.
- Click the issue ID to open an issue in a new browser tab. Use this option to update the estimation and spent time for the corresponding task.
- When the total duration of the tasks exceeds the width of the report, click the bar at the bottom of the report to scroll through the timeline. You can also drag the bar to zoom in and out on the timeline.
Visual Presentation
The report uses visual cues to represent different types of information.
- The current date is highlighted in the timeline. A vertical line is drawn down the chart to show the end of the day.
- The color of the bars reflects the current status of each task.
- The progress towards completion of a task is displayed as a percentage to the left of each bar.
- The relationship between parent tasks and subtasks is represented by two vertical lines. The line on the left represents the start date of the earliest subtask. The line on the right represents the end date of the latest subtask.
- The relationship between dependent tasks is represented by an arrow. The arrow is drawn from the end date of the predecessor task to the start date of the successor task.
- In the Actual view, the spent time for unresolved tasks is drawn as a dark horizontal line at the bottom of the bar for each subtask.
Prerequisites
For best results, you should configure and use YouTrack according to the following guidelines:
- Enable and configure time tracking in each project that you want to show on the report.
If the system-wide time tracking settings for your YouTrack server are configured incorrectly, the report cannot be calculated. For example, the work days are not defined or the hours per day are set to zero. For more information, see System-wide Time Tracking Settings.
- Enter values in the Estimation field for each issue.
- Use time tracking to enter work items for each issue.
- Use link types that represent dependencies between tasks and aggregations.
You should also consider using the Type field to categorize issues that you want to select as top-level issues for the report. This makes it easier to define the query. For example, assign parent issues the Feature type and assign subtasks the Task type. You can then set the query to display all unresolved issues that are assigned the Feature type.
Settings
Use the following settings to configure this report.
Example
A report with the following settings displays the project timeline for the Inception Release Planning project. With unlimited capacity, the number of work days that are required to complete all tasks equals the longest string of dependent tasks. The chart is drawn for the Actual view.
| Setting | Value |
|---|---|
| Project | Inception Release Planning |
| Start Date | 8/24/2016 |
| Estimation Field | Estimation |
| Spend Time Field | Spent time |
| Aggregation Link | parent for |
| Dependency Link | depends on |
| Max Task Tree Depth | 2 |

Here is the same chart with the Capacity limited to 2 tasks. Notice how limiting the work in progress increases the number of work days that are required to complete all tasks. With limited capacity, the chart is automatically drawn for the Actual view. The slider at the bottom of the report lets you scroll horizontally through the chart.

When we increase the capacity to 4 tasks, we see how much faster we can complete all tasks with a few more resources.
This example only shows two of the tasks that are currently in progress. The other two appear further down the chart.

Calculations
The values that are displayed in the tooltips for parent tasks are calculated as follows:
| Value | Description |
|---|---|
| estimated duration | The estimated amount of time that is required to resolve the parent task. This represents the amount of time between the start of the earliest subtask and the estimated completion of the latest subtask. This value is calculated using the longest duration for the cumulative estimation of all subtasks with dependencies. If there are no dependencies between subtasks, this is the estimation for the subtask with the longest duration. The value that is stored in the estimation field for the parent task is ignored. |
| overestimation | This value is shown when the estimated duration is greater than the cumulative spent time.
The cumulative spent time is the longest total duration of spent time in a single chain of dependent subtasks.
This value is subtracted from the estimated duration.
If there are no dependencies between subtasks, the largest amount of spent time in a single subtask is subtracted from the estimated duration.
For an example, see Sample Calculations. |
| underestimation | This value is shown when the estimated duration is less than the cumulative spent time.
The cumulative spent time is the longest total duration of spent time in a single chain of dependent subtasks.
This value is subtracted from the estimated duration.
If there are no dependencies between subtasks, the largest amount of spent time in a single subtask is subtracted from the estimated duration.
The negative number that is returned by the calculation is displayed as a positive number on the chart.
For an example, see Sample Calculations. |
| estimated effort | The sum of the estimation for each subtask. This value corresponds with the total working time that is required to resolve the parent task. |
| aggregated spent time | The sum of the spent time for each subtask. |
| remaining effort | This value is shown only when the parent task is underestimated. This value is calculated by subtracting the spent time form the estimation of all subtasks that are not underestimated. |
The values that are displayed in the tooltips for subtasks are calculated as follows:
Sample Calculations
This example demonstrates how overestimation and underestimation values are calculated for parent tasks. The following information is displayed on the report:
- There are three parent tasks.
- Each summary task has three subtasks. The second and third subtasks depend on the completion of the previous subtask.
- Each subtask is estimated to require two days.
- All of the subtasks are resolved.
The Estimated view is drawn as follows:

When we toggle to the Actual view, the amount of spent time is reflected in the report.

Let's take a closer look at each parent task to see how spent time is used to calculate over- and underestimation values.
- In the first parent task, the second subtask was overestimated by one day. As a result, the parent task shows an overestimation.
The overestimated value is calculated by subtracting the total duration of spent time entered in each subtask from the estimated duration, as follows:
6d - (2d + 1d + 2d) = 1d - In the second parent task, the first subtask was overestimated by one day, but the second task was underestimated by one day.
The third subtask was completed on time. As a result, the parent task was completed on time. The completion time is calculated as follows:
6d - (1d + 3d + 2d) = 0d - In the third parent task, the second task was underestimated by one day.
All other subtasks were completed on time. As a result, the parent task was underestimated. The underestimation is calculated as follows:
6d - (2d + 3d + 2d) = -1d